Ongoing
Semanggar and Layang 2 Water Treatment Plants
New treatment plants to keep water supply ahead of demand from data centres, industry and population growth. Johor's 48 plants have 2,352 million litres a day (MLD) of design capacity; the state aims for about 3,000 MLD by 2030.
02/05 milestones
Next2026Semanggar plant (50 MLD) completed, supplying Kulai and Sedenak
Timeline
- Four-plant, RM1.41 billion water programme announced for data centre demand
- RM184 million confirmed for Semanggar (50 MLD) and Layang 2 Phase 2 (160 MLD)
- 2026Semanggar plant (50 MLD) completed, supplying Kulai and Sedenak
- 2027Layang 2 Phase 2 (160 MLD) completed, supplying Johor Bahru and Iskandar Puteri
- Date not setSemanggar 3 and Kayu Ara Pasong (290 MLD combined) move from design to construction
Sources
Last checked 7 Nov 2026. Johor Signal is an independent tracker; every milestone links to a public report. Spot an update? Email g.w.e.wee@soton.ac.uk.