Signal Insights

What the tracker's own records say: which projects are moving, which dates have slipped, what is due next, and how Johor's headline numbers are trending.

Moved in last 90 days9/19Projects with a new milestone since late July
Typical quiet spell33 daysMedian days since the last milestone, projects in progress
Milestones in 202637Logged so far this year across all projects
Dates slipped6/6Projects whose tracked target moved later
Due by April 20279Dated milestones in the next six months

Signal strength

A 0–100 score for each project still in progress, from how recently it moved, how far along it is, and whether its dates are holding. Hover a row for the breakdown.

Projects in progress

Higher is healthier
Recency (40)Progress (30)Schedule (30)
YTL Green Data Center Park and AI CloudLast move 33 days ago · ongoingStrong91
JS-SEZ Tax Incentive PackageLast move 29 days ago · ongoingStrong89
Ibrahim Technopolis (IBTEC) and Sedenak Tech ParkLast move 14 days ago · ongoingStrong88
Johor Bahru–Singapore RTS LinkLast move 11 days ago · ongoingStrong84
MyNIISe QR Clearance at Johor CheckpointsLast move 132 days ago · ongoingStrong81
Gerbang Nusajaya Industrial ParkLast move 3 days ago · planningStrong80
Forest City Special Financial ZoneLast move 145 days ago · ongoingStrong79
Port of Tanjung Pelepas Berth Zero ExpansionLast move 30 days ago · ongoingStrong79
JS-SEZ Masterplan and Investment BlueprintLast move 5 days ago · ongoingStrong74
Nexus Sedenak Industrial and Supply-Chain HubLast move 8 days ago · planningStrong74
Senai Airport City Phase 3Last move 118 days ago · ongoingSteady67
Johor Bahru Elevated Autonomous Rapid Transit (E-ART)Last move 29 days ago · planningSteady60
Invest Malaysia Facilitation Centre Johor (IMFC-J)Last move 237 days ago · ongoingSteady54
Pengerang Biorefinery and SAF StorageLast move 362 days ago · ongoingSteady48
Semanggar and Layang 2 Water Treatment PlantsLast move 353 days ago · ongoingWeak43
Kuala Lumpur–Singapore High-Speed RailLast move 396 days ago · planningWeak20

Delivered and not scored: Gemas–Johor Bahru Electrified Double Track, KTM Shuttle Selatan Commuter Service, Singapore Passport-Free Land Checkpoint Clearance.

Momentum

Milestones reached per quarter, all projects

Watchlist

Dated milestones due in the next 12 months
Dec 2026
  • Johor Bahru–Singapore RTS LinkFares announced jointly by both governments and RTS Operations · By end-2026
  • Johor Bahru–Singapore RTS LinkAll system checks and trial runs completed · By 31 December 2026
  • JS-SEZ Masterplan and Investment BlueprintMasterplan and investment blueprint launched at the 13th Malaysia–Singapore Leaders' Retreat · 4–5 December 2026
  • Forest City Special Financial ZoneFamily office assets under management reach the RM2 billion target
  • Ibrahim TechnopolisTNB 500kV substation at STeP West completed · 2026
  • Semanggar and Layang 2 Water Treatment PlantsSemanggar plant (50 MLD) completed, supplying Kulai and Sedenak · 2026
Feb 2027
  • Johor Bahru–Singapore RTS LinkPassenger service begins · February 2027 (target)
  • MyNIISe QR Clearance at Johor CheckpointsSingle-point clearance goes live at the RTS Link Bukit Chagar CIQ · February 2027 (target)
Mar 2027
  • JS-SEZ Masterplan and Investment BlueprintFirst joint Johor–Singapore investment forum held · By Q1 2027
Jun 2027
  • YTL Green Data Center Park and AI CloudA further 200MW of data centre capacity completed at Kulai

Date drift

How target dates have moved for projects with a published timeline. Grey dot = first target, orange = latest, green = delivered. Dashed line = still open.

Zone scorecard

Progress and activity by flagship zone. A project spanning several zones counts in each.

ZoneProjectsMilestones reachedLast activityAvg signal
AJohor Bahru Waterfront627/3611 days ago67
BIskandar Puteri519/293 days ago57
CTanjung Pelepas16/830 days ago79
DTanjung Langsat – Kong Kong14/4144 days ago—
ESenai – Skudai29/1229 days ago64
FKulai – Sedenak622/318 days ago74
GDesaru – Penawar0No tracked projects yet
HPengerang (PIPC)13/5362 days ago48
IForest City SFZ15/6145 days ago79
AllZone-wide314/185 days ago72
SGCross-border314/1911 days ago52

Johor indicators

Headline figures from official releases and company reports, plotted where a series exists.

Approved investment, Johor

RM billion

MIDA (2023, 2024, 2025); state exco via IndependentSG (H1 2026). 2024 is the figure as first reported; later revisions put growth into 2025 at 69.6% (Business Today).

Tanjung Pelepas throughput

Million TEU

PortCalls (2021, 2024), MMC Ports (2025), FMT (2029 target). 2022–2023 not shown.

Median monthly wage, Malaysia

RM, all employees

DOSM Salaries & Wages Survey 2024 and 2025. A Johor breakdown is not published in these releases.

Iskandar Malaysia, since 2006RM525.3 bilCumulative investment, 137% of the RM383 bil target (IRDA, Oct 2026)
Approved JS-SEZ investmentRM88.8 bilJanuary 2025 to June 2026; 45% already being implemented (joint ministerial statement, Nov 2026). Budget 2027 cited RM132 bil for the same period.
Jobs linked to approved projects28,755Potential jobs; 12,796 of them from projects already implemented (joint ministerial statement, Nov 2026)
Data centre capacity live1,110 MWOperational IT load in Johor, with 65 more projects at some stage of approval (The Straits Times via Malay Mail, Nov 2026)
Approved data centre projects16 of 27Located in Johor, of RM225.97 bil approved nationally (Digital Ministry, Oct 2026)
MyNIISe QR clearances19.48 milTransactions at the two Johor checkpoints to 28 June 2026 (Bernama)

Sources: MIDA 2023 · MIDA 2024 · MIDA 2025 fact sheet · Business Today · H1 2026 · PortCalls · MMC Ports · FMT · DOSM via Business Today · IRDA via The Edge · Budget 2027 · Bernama

Analysis lab

Statistical reads of the tracker and the headline series. Small samples, so treat each result as directional; the method is printed under every chart.

Delivery pace forecast

Cumulative milestones since Jan 2024, with a Poisson projection to Jun 2027
LoggedProjection (median)80% and 95% ranges
3.50Milestones / month (λ)
+28Expected by Jun 2027
18–3995% range
2.06×2026 vs 2025 rate
1.15–3.6895% CI of ratio

Activity is running at 3.5 milestones a month. January–October 2026 logged 35 against 17 in the same months of 2025, a rate ratio of 2.06 (95% CI above 1, so the pick-up is statistically clear). On this pace the tracker should log about 28 more by June 2027.

Method: monthly milestone counts are treated as Poisson events. λ is the trailing 12-month mean. Bands are Poisson quantiles of λ×h for horizon h months. Rate ratio compares Jan–Oct 2026 with Jan–Oct 2025, 95% CI on the log scale. Year-only dates excluded.

Time to next milestone

Kaplan–Meier survival of quiet spells
149 dMedian gap
66%Still quiet at 90 days
44%Still quiet at 180 days
57/16Gaps / open spells

Half of all quiet spells end within 149 days. About 44% run past six months, so long silences are common in public reporting; a quiet project is not necessarily a stalled one.

Method: each gap between consecutive milestones of a project is an event; each project's current quiet spell is right-censored at 7 Nov 2026. S(t) is the share of spells still unbroken after t days. Shaded band is a 95% Greenwood interval.

Is the port target on pace?

Tanjung Pelepas, million TEU
ActualAt 2021–25 growthPath needed for 16m by 2029

Throughput grew 5.8% a year from 2021 to 2025. The 2029 target needs only 3.3%. At past pace the port passes 16 million TEU in 2028, ahead of schedule, provided capacity keeps up; the September cyber attack is a reminder that disruptions can dent a year.

Method: compound annual growth rates from the reported annual totals (2021, 2024, 2025). Projection extends the 2021–25 CAGR; the required path is the CAGR from 2025 to the stated 2029 target.

2026 investment run-rate

Johor approved investment vs the state's RM100 bil target

Half-way through 2026, Johor has 59% of its RM100 bil target, ahead of the 50% a straight-line pace would need. A simple run-rate points to about RM119 bil for the year, which would sit just above 2025's record RM110 bil but short of the RM140 bil goal.

Method: H1 2026 approvals (RM59.4 bil, state exco) against the RM100 bil annual target cited in September. The Menteri Besar cited a higher RM140 bil goal in March. Approvals are lumpy, so a straight annualisation overstates certainty.

Jobs per RM1 billion approved

Capital intensity of approved investment
Johor 2023443 jobs
Johor 2025223 jobs
Malaysia 2024547 jobs
Malaysia 2025574 jobs

Each RM1 bil approved in Johor in 2025 came with about 223 jobs, about half the 2023 ratio, while the national mix created 2.6× as many per ringgit. That fits a shift toward capital-heavy projects such as data centres, and it means investment headlines will not translate one-for-one into hiring.

Method: expected jobs divided by approved investment (RM bil) from MIDA and state releases: Johor 2023 (19,053 jobs, RM43.0 bil), Johor 2025 (24,584, RM110.0 bil), Malaysia 2024 (207,000+, RM378.5 bil), Malaysia 2025 (244,902, RM426.7 bil).

How the score works

Recency (40 points). Full marks if the project's latest milestone is today, falling in a straight line to zero at 365 days. Year-only dates count as 1 July; month-only dates as the 15th.

Progress (30 points). Milestones reached divided by milestones tracked, including the next and later ones.

Schedule (30 points). Starts at 30. Loses 10 if the next milestone has no date, 2.5 per month a tracked target has slipped (capped at 20), and 20 if a target has been withdrawn with no new date.

The score reflects public reporting, not the project's real condition: a project that is busy but quiet in the news will score lower than it deserves. Treat it as a prompt to look closer, not a verdict.