Signal Insights
What the tracker's own records say: which projects are moving, which dates have slipped, what is due next, and how Johor's headline numbers are trending.
Signal strength
A 0–100 score for each project still in progress, from how recently it moved, how far along it is, and whether its dates are holding. Hover a row for the breakdown.
Projects in progress
Higher is healthierDelivered and not scored: Gemas–Johor Bahru Electrified Double Track, KTM Shuttle Selatan Commuter Service, Singapore Passport-Free Land Checkpoint Clearance.
Momentum
Milestones reached per quarter, all projectsWatchlist
Dated milestones due in the next 12 months- Johor Bahru–Singapore RTS LinkFares announced jointly by both governments and RTS Operations · By end-2026
- Johor Bahru–Singapore RTS LinkAll system checks and trial runs completed · By 31 December 2026
- JS-SEZ Masterplan and Investment BlueprintMasterplan and investment blueprint launched at the 13th Malaysia–Singapore Leaders' Retreat · 4–5 December 2026
- Forest City Special Financial ZoneFamily office assets under management reach the RM2 billion target
- Ibrahim TechnopolisTNB 500kV substation at STeP West completed · 2026
- Semanggar and Layang 2 Water Treatment PlantsSemanggar plant (50 MLD) completed, supplying Kulai and Sedenak · 2026
- Johor Bahru–Singapore RTS LinkPassenger service begins · February 2027 (target)
- MyNIISe QR Clearance at Johor CheckpointsSingle-point clearance goes live at the RTS Link Bukit Chagar CIQ · February 2027 (target)
- JS-SEZ Masterplan and Investment BlueprintFirst joint Johor–Singapore investment forum held · By Q1 2027
- YTL Green Data Center Park and AI CloudA further 200MW of data centre capacity completed at Kulai
Date drift
How target dates have moved for projects with a published timeline. Grey dot = first target, orange = latest, green = delivered. Dashed line = still open.
Zone scorecard
Progress and activity by flagship zone. A project spanning several zones counts in each.
| Zone | Projects | Milestones reached | Last activity | Avg signal |
|---|---|---|---|---|
| AJohor Bahru Waterfront | 6 | 27/36 | 11 days ago | 67 |
| BIskandar Puteri | 5 | 19/29 | 3 days ago | 57 |
| CTanjung Pelepas | 1 | 6/8 | 30 days ago | 79 |
| DTanjung Langsat – Kong Kong | 1 | 4/4 | 144 days ago | — |
| ESenai – Skudai | 2 | 9/12 | 29 days ago | 64 |
| FKulai – Sedenak | 6 | 22/31 | 8 days ago | 74 |
| GDesaru – Penawar | 0 | No tracked projects yet | ||
| HPengerang (PIPC) | 1 | 3/5 | 362 days ago | 48 |
| IForest City SFZ | 1 | 5/6 | 145 days ago | 79 |
| AllZone-wide | 3 | 14/18 | 5 days ago | 72 |
| SGCross-border | 3 | 14/19 | 11 days ago | 52 |
Johor indicators
Headline figures from official releases and company reports, plotted where a series exists.
Approved investment, Johor
RM billionMIDA (2023, 2024, 2025); state exco via IndependentSG (H1 2026). 2024 is the figure as first reported; later revisions put growth into 2025 at 69.6% (Business Today).
Tanjung Pelepas throughput
Million TEUPortCalls (2021, 2024), MMC Ports (2025), FMT (2029 target). 2022–2023 not shown.
Median monthly wage, Malaysia
RM, all employeesDOSM Salaries & Wages Survey 2024 and 2025. A Johor breakdown is not published in these releases.
Sources: MIDA 2023 · MIDA 2024 · MIDA 2025 fact sheet · Business Today · H1 2026 · PortCalls · MMC Ports · FMT · DOSM via Business Today · IRDA via The Edge · Budget 2027 · Bernama
Analysis lab
Statistical reads of the tracker and the headline series. Small samples, so treat each result as directional; the method is printed under every chart.
Delivery pace forecast
Cumulative milestones since Jan 2024, with a Poisson projection to Jun 2027Activity is running at 3.5 milestones a month. January–October 2026 logged 35 against 17 in the same months of 2025, a rate ratio of 2.06 (95% CI above 1, so the pick-up is statistically clear). On this pace the tracker should log about 28 more by June 2027.
Method: monthly milestone counts are treated as Poisson events. λ is the trailing 12-month mean. Bands are Poisson quantiles of λ×h for horizon h months. Rate ratio compares Jan–Oct 2026 with Jan–Oct 2025, 95% CI on the log scale. Year-only dates excluded.
Time to next milestone
Kaplan–Meier survival of quiet spellsHalf of all quiet spells end within 149 days. About 44% run past six months, so long silences are common in public reporting; a quiet project is not necessarily a stalled one.
Method: each gap between consecutive milestones of a project is an event; each project's current quiet spell is right-censored at 7 Nov 2026. S(t) is the share of spells still unbroken after t days. Shaded band is a 95% Greenwood interval.
Is the port target on pace?
Tanjung Pelepas, million TEUThroughput grew 5.8% a year from 2021 to 2025. The 2029 target needs only 3.3%. At past pace the port passes 16 million TEU in 2028, ahead of schedule, provided capacity keeps up; the September cyber attack is a reminder that disruptions can dent a year.
Method: compound annual growth rates from the reported annual totals (2021, 2024, 2025). Projection extends the 2021–25 CAGR; the required path is the CAGR from 2025 to the stated 2029 target.
2026 investment run-rate
Johor approved investment vs the state's RM100 bil targetHalf-way through 2026, Johor has 59% of its RM100 bil target, ahead of the 50% a straight-line pace would need. A simple run-rate points to about RM119 bil for the year, which would sit just above 2025's record RM110 bil but short of the RM140 bil goal.
Method: H1 2026 approvals (RM59.4 bil, state exco) against the RM100 bil annual target cited in September. The Menteri Besar cited a higher RM140 bil goal in March. Approvals are lumpy, so a straight annualisation overstates certainty.
Jobs per RM1 billion approved
Capital intensity of approved investmentEach RM1 bil approved in Johor in 2025 came with about 223 jobs, about half the 2023 ratio, while the national mix created 2.6× as many per ringgit. That fits a shift toward capital-heavy projects such as data centres, and it means investment headlines will not translate one-for-one into hiring.
Method: expected jobs divided by approved investment (RM bil) from MIDA and state releases: Johor 2023 (19,053 jobs, RM43.0 bil), Johor 2025 (24,584, RM110.0 bil), Malaysia 2024 (207,000+, RM378.5 bil), Malaysia 2025 (244,902, RM426.7 bil).
How the score works
Recency (40 points). Full marks if the project's latest milestone is today, falling in a straight line to zero at 365 days. Year-only dates count as 1 July; month-only dates as the 15th.
Progress (30 points). Milestones reached divided by milestones tracked, including the next and later ones.
Schedule (30 points). Starts at 30. Loses 10 if the next milestone has no date, 2.5 per month a tracked target has slipped (capped at 20), and 20 if a target has been withdrawn with no new date.
The score reflects public reporting, not the project's real condition: a project that is busy but quiet in the news will score lower than it deserves. Treat it as a prompt to look closer, not a verdict.