Gemas–Johor Bahru Electrified Double Track

Lead / parties
Ministry of Transport / KTMB / SIPP–YTL JV
Reported value
Not disclosed
Flagship zone
Kulai – Sedenak, Johor Bahru Waterfront
Status
Completed · 3 of 3 milestones reached

Electrification and double-tracking of the 192 km Gemas–Johor Bahru stretch, completing an electric rail corridor from Padang Besar to JB Sentral. The ETS now runs KL Sentral to JB Sentral in about four hours 20 minutes, down from about seven hours.

03/03 milestones

Timeline

  1. 2017Construction began
  2. March 2025ETS service extended as far south as Segamat
  3. Line launched at Kempas Baru; ETS services reach JB Sentral

Schedule changes · Full completion

  1. As of 14 March 202421 April 2025Loke
  2. As of 7 January 2025Q3 2025Bernama
  3. As of 11 December 2025Opened 11 Dec 2025The Edge

Sources

  1. paultan.org — ETS reaches Segamat (Mar 2025)
  2. RailTravel Station — Earlier completion targets: April 2025, then Q3 2025
  3. The Edge — Gemas–JB line launched (Dec 2025)
  4. MyRumahBaru — ETS KL–JB guide, project began 2017 (Apr 2026)