Completed
Gemas–Johor Bahru Electrified Double Track
Electrification and double-tracking of the 192 km Gemas–Johor Bahru stretch, completing an electric rail corridor from Padang Besar to JB Sentral. The ETS now runs KL Sentral to JB Sentral in about four hours 20 minutes, down from about seven hours.
03/03 milestones
Final11 December 2025Line launched at Kempas Baru; ETS services reach JB Sentral
Timeline
- 2017Construction began
- March 2025ETS service extended as far south as Segamat
- Line launched at Kempas Baru; ETS services reach JB Sentral
Schedule changes · Full completion
- As of 14 March 202421 April 2025Loke
- As of 7 January 2025Q3 2025Bernama
- As of 11 December 2025Opened 11 Dec 2025The Edge
Sources
Last checked 7 Nov 2026. Johor Signal is an independent tracker; every milestone links to a public report. Spot an update? Email g.w.e.wee@soton.ac.uk.