Ongoing

Johor Bahru–Singapore RTS Link

Lead / parties
MRT Corp / LTA Singapore / RTS Operations (Prasarana–SMRT JV)
Reported value
RM10 billion (est.)
Flagship zone
Johor Bahru Waterfront, Cross-border
Status
Ongoing · 6 of 9 milestones reached

A 4 km cross-border rail shuttle between Bukit Chagar in Johor Bahru and Woodlands North in Singapore. Co-located CIQ means passengers clear both countries' immigration once, at departure. It is designed for 10,000 passengers an hour in each direction and about 40,000 riders a day, with a journey of about five minutes.

06/09 milestones

Timeline

  1. 2021Woodlands North station construction began
  2. Physical works nearly complete; e-gates installed at the Bukit Chagar CIQ complex
  3. All Malaysian-side station and rail infrastructure completed; final integration testing under way
  4. Woodlands North station completed
  5. Opening moved to February 2027, subject to independent safety certification and final approvals
  6. Singapore and Malaysian agencies run a joint emergency exercise on the line, closing at Wadi Hana depot
  7. By end-2026Fares announced jointly by both governments and RTS Operations
  8. By 31 December 2026All system checks and trial runs completed
  9. February 2027 (target)Passenger service begins

Schedule changes · Passenger service start

  1. As of June 2025End-2026LTA
  2. As of 3 April 2026January 2027AsiaOne
  3. As of 2 October 2026February 2027LTA/MOT joint statement

Sources

  1. LTA Singapore — RTS Link project page
  2. AsiaOne — On track for January 2027; e-gates installed (Apr 2026)
  3. The Star — Fare and opening date to be announced jointly (Aug 2026)
  4. The Rakyat Post — Malaysian side complete, final testing (Aug 2026)
  5. Malay Mail — Woodlands North station completed (Sep 2026)
  6. paultan.org — Woodlands North completed, service in 2027 (Sep 2026)
  7. Land Transport Guru — RM10 billion project cost estimate
  8. Malay Mail — Fares by year-end; service from February 2027 (Oct 2026)
  9. The Independent SG — Tests and trial runs due by 31 Dec (Oct 2026)
  10. Must Share News — Joint emergency exercise on the RTS Link (Oct 2026)

Last checked 7 Nov 2026. Johor Signal is an independent tracker; every milestone links to a public report. Spot an update? Email g.w.e.wee@soton.ac.uk.