Kuala Lumpur–Singapore High-Speed Rail

Lead / parties
MyHSR Corp / Ministry of Transport
Reported value
Not disclosed
Flagship zone
Iskandar Puteri, Cross-border
Status
Planning · 4 of 6 milestones reached

A proposed 350 km high-speed line between Kuala Lumpur and Singapore with a Johor station at Iskandar Puteri. It was cancelled in 2021 and is being revived as a private sector–led project; the government has said it will not fund it directly.

04/06 milestones

Timeline

  1. January 2021Original bilateral project terminated
  2. July 2023MyHSR called for private-sector concept proposals
  3. Prime Minister said revival depends on full private-sector participation
  4. Transport Ministry finalising key project parameters ahead of an RFP
  5. Date not setRequest for proposal issued
  6. Date not setNew bilateral agreement negotiated with Singapore

Schedule changes · Start of operations

  1. As of December 20162026 (original agreement)MyHSR
  2. As of 7 October 2025No date; RFP not yet issuedThe Edge

Sources

  1. paultan.org — Revival only with private sector (Jan 2025)
  2. paultan.org — Project timeline recap (Dec 2024)
  3. The Edge — Development model still undecided (Oct 2025)

Last checked 7 Nov 2026. Johor Signal is an independent tracker; every milestone links to a public report. Spot an update? Email g.w.e.wee@soton.ac.uk.