Port of Tanjung Pelepas Berth Zero Expansion
Malaysia's largest container terminal is adding Berth Zero, a 360 m berth with four quay cranes and a yard ready for electric rubber-tyred gantry cranes. Volumes have climbed since the port became the main hub for the Maersk–Hapag-Lloyd Gemini network.
06/08 milestones
NextDate not setBerth Zero enters operation
Timeline
- June 2024RM750 million upgrade announced to lift capacity to 12.5 million TEU
- Berth Zero contract awarded to the MMC Engineering–Antara Koh JV
- Record month reported: nearly 1.3 million TEU handled in May 2026
- Cyber attack forces a temporary halt to container operations; phased restart from 10 September
- Transport Minister backs speeding up the second phase, taking capacity toward 48 million TEU a year
- Rollout of 52 electric terminal tractors completed
- Date not setBerth Zero enters operation
- 2029Annual throughput reaches 16 million TEU, up from a record 14 million in 2025
Sources
- Baird Maritime — RM750 million capacity expansion (Jun 2024)
- The Star — Berth Zero awarded (Oct 2025)
- Container News — Berth Zero scope (Oct 2025)
- FMT — 16 million TEU target by 2029 (Jun 2026)
- WorldCargo News — Operations resume after cyber attack (Sep 2026)
- The Edge — Loke backs second-phase expansion (Oct 2026)
- WorldCargo News — 52 electric terminal tractors (Oct 2026)