Port of Tanjung Pelepas Berth Zero Expansion

Lead / parties
Port of Tanjung Pelepas (MMC 70% / APM Terminals 30%)
Reported value
Not disclosed
Flagship zone
Tanjung Pelepas
Status
Ongoing · 6 of 8 milestones reached

Malaysia's largest container terminal is adding Berth Zero, a 360 m berth with four quay cranes and a yard ready for electric rubber-tyred gantry cranes. Volumes have climbed since the port became the main hub for the Maersk–Hapag-Lloyd Gemini network.

06/08 milestones

Timeline

  1. June 2024RM750 million upgrade announced to lift capacity to 12.5 million TEU
  2. Berth Zero contract awarded to the MMC Engineering–Antara Koh JV
  3. Record month reported: nearly 1.3 million TEU handled in May 2026
  4. Cyber attack forces a temporary halt to container operations; phased restart from 10 September
  5. Transport Minister backs speeding up the second phase, taking capacity toward 48 million TEU a year
  6. Rollout of 52 electric terminal tractors completed
  7. Date not setBerth Zero enters operation
  8. 2029Annual throughput reaches 16 million TEU, up from a record 14 million in 2025

Sources

  1. Baird Maritime — RM750 million capacity expansion (Jun 2024)
  2. The Star — Berth Zero awarded (Oct 2025)
  3. Container News — Berth Zero scope (Oct 2025)
  4. FMT — 16 million TEU target by 2029 (Jun 2026)
  5. WorldCargo News — Operations resume after cyber attack (Sep 2026)
  6. The Edge — Loke backs second-phase expansion (Oct 2026)
  7. WorldCargo News — 52 electric terminal tractors (Oct 2026)

Last checked 7 Nov 2026. Johor Signal is an independent tracker; every milestone links to a public report. Spot an update? Email g.w.e.wee@soton.ac.uk.