A biorefinery at the Pengerang Integrated Complex that will process about 650,000 tonnes a year of feedstock into sustainable aviation fuel, renewable diesel and bio-naphtha, supported by 272,000 m³ of dedicated storage at Pengerang Terminals (Two).
03/05 milestones
NextH1 2028Storage expansion completed
Timeline
- July 2024Final investment decision by PETRONAS, Eni and Euglena; Samsung awarded a US$955 million build contract
- 25-year storage agreement signed; 272,000 m³ terminal expansion begins
- Biorefinery groundbreaking ceremony held in Pengerang
- H1 2028Storage expansion completed
- 2H 2028Biorefinery begins operations